Pembangunan Rumah Pompa Patra Tuntas Dikerjakan

Patra Pump House Construction Completed

West Jakarta Water Resources Sub-agency has completed the construction of pump house on Jalan Patra, RT 08/02, Duri Kepa, Kebon Jeruk.

Now we are installing two pump units with each capacity 500 liters per second

Sub-agency Head, Purwanti, said the construction which was started in October 2023 ago has been handed over from contractor on February 3, 2024.

Patra Pump House Construction Reaches 95 Percent

"Now we are installing two pump units with each capacity 500 liters per second," she said, Monday (2/12).

Purwanti admitted the pump units installation have reached 95 percent and is targeted to complete by mid of February 2024.

"it is hoped the pumps will eliminate inundation on Jalan Patra," she hoped.

Yoyo Kusnadi (55), a local resident,  admitted happy with the existence of this pump house. He hopes the pump house will eliminate inundation.

"Jalan Patra is prone to inundation during rainy season. It is hoped the pump house will eliminate it," he hoped.

Linked News
Popular News indeks
  1. Transjabodetabek PIK 2-Blok M Route Serves 1.4 Million Passengers

    access_time24-05-2026 remove_red_eye1483 personAldi Geri Lumban Tobing
  2. Fire at Pondok Bambu Allegedly Triggered by Electrical Short

    access_time19-05-2026 remove_red_eye1399 personNurito
  3. Kultura Market in Pademangan Barat Attracts Crowds

    access_time22-05-2026 remove_red_eye1072 personAnita Karyati
  4. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye1039 personAldi Geri Lumban Tobing
  5. Inundation on DI Panjaitan Road Recede

    access_time20-05-2026 remove_red_eye861 personNurito